The timeline below is for both the 74th Avenue and Alden Street projects, and is subject to change.
-
Surveys and studies (completed)
May-October 2020 -
Preliminary designs (current)
Through January 2021 -
Final designs
January-May 2021 -
Right-of-way acquisition discussions
March-August 2021 -
Contractor bids process
July-August 2021 -
Start of construction
September 2021 -
Projects completed
May 2022